2008 Tentative Build Schedule

Both Saturday and week day work can be scheduled for groups or individuals

Volunteers please directly contact our Construction Manager at (219) 363-7869 or

Office at (219) 324-7510.

 As you can see, our schedule is geared toward specific weekly tasks that are sometimes subject to change. So in order to place volunteers with work experience, call in advance.

****************

Site Preparation, Excavation and Foundation March 15 - April 15

Floor Deck and Temporary Electric April 15 - April 30

 

Week 1 Saturday, May 3rd
Frame Walls (interior/exterior) & Sheathing Mechanicals Complete & Tested
Corner Sheathing, Top Plates and bracing Trusses

Week 2 Saturday May 10th                                                        Week 7 Saturday, June 21
                                                                                                     
Paint Walls & Ceilings
Roof Sheathing & Fascia Install                                                                                                 Back Door Porch/Patio
Prepare Roof (paper, drip edge & shields)                                                                              Insulate Attic and Install Interior Doors
Install Windows & Exterior Doors

House Wrap/Seal Windows and Doors                                                          Week 8 Saturday, June 28
                                                                                                      
Flooring Kitchen, Bath, Utility and Entry
Week 3 Saturday, May 17th                                                                                   Build Shed
Shingles                                                                                                                                          Insulate and Clean Basement
Begin Siding

Begin Plumbing, Heating & Electric                                                            Saturday July 5th
                                                                                                      4th of July Weekend
Saturday, May 24th
Memorial Day Weekend                                                              Week 9 Saturday July 12th
                                                                                                     
Install Closet Doors
Week 4 Saturday, May 31st                                                                                   Interior Trim
Complete Siding                                                                                                                            Install Closet Shelving
Gutters & Downspouts                                                                                                                 Kitchen/Bath Cabinets & Countertops
Driveway

Complete All Mechanical Rough-in                                                                                            Week 10 Saturday, July 19th
Install Blocking & Nailers                                                                                                             Install Plumbing & Electric Fixtures
                                                                                                                                                          Install Appliances & Window Coverings

Week 5 Saturday, June 7th                                                         
Remove building materials/Clean Site
Wall Insulation                                                                                                                               Install storm doors, shutters, mailbox, etc.
Drywall Ceilings                                                                                                                             Install Door Handles & Locks

Landscaping
                                                                                                      July 21st-August 8th
Week 6 Saturday, June 14th                                                     
Carpet Installation
Complete Drywall                                                                                                                         Final Cleaning
Paint/Stain Doors & Trim                                                                                                            Complete Unfinished Exterior Items

                                                               Dedication Sunday, August 10th, 2008
 

 

 